SHORT-TERM CORRIDORS (2011-2015)
- Avenida 80 corridor
- Line C commercial operation
- Multipurpose railway system corridor, phase I
- New station between Industriales and Poblado
MEDIUM-TERM CORRIDORS (2016-2020)
- Avenida Oriental to Avenida 80 with Calle 80 corridor
- Project of Line A expansion to the north (Navarra)
- Avenida 34 corridor between Aguacatala station and Palos Verdes
- San Antonio de Prado – La Estrella corridor
- North-west cable corridor
- Quebrada La García corridor
- New station between Envigado and Itagüí (Primavera)
- New station between Madera and Acevedo
LONG-TERM CORRIDORS (2021-2030)
- Multipurpose railway system corridor, phases I, II and III
- El Salado – Ayurá corridor
- Alpujarra – El Vergel corridor
- El Poblado – Terminal del Sur – Avenida 80 corridor
- Itagüí Metrocable (Envigado – Calatrava)
- Connection to Eastern Antioquia
- Sabaneta corridor
- Transportation system in Eastern Antioquia
- Santa Mónica corridor
- New station between Poblado and Aguacatala